to the first dated response from any city department where activity data is available.
Bellevue permit data
What 503 new-home permits reveal.
See how long recent Bellevue permits took, which city teams responded first, how often plans needed changes, and where active permits are waiting. Filter by builder for more context, but remember that every project is different.
for every assigned department to finish the first review where the full round is public.
across permits with complete public review activity.
median application-to-issuance time among 322 permits with both dates.
Showing the full 503-permit sample. 291 permits currently have a reviewed custom or spec builder label.
Builder comparison
Timing across the full sample
Custom and spec groups use reviewed builder labels and recalculate with every weekly snapshot. Spec builders often repeat teams and processes, but the public data cannot isolate why one group was faster or slower.
Project mix
What is being built
Normalized from the public project description so unlike projects can be separated.
Construction
Issued permit to final approval
Based on 101 permits with both issued and finaled dates.
Location context
Where projects are concentrated
Neighborhood names come from the public parcel geocoder and are directional rather than formal boundaries.
Supplemental parcel context
Most common assessor zoning labels
These labels support broad comparisons only and are not city zoning determinations. Confirm current zoning in Bellevue's official map.
Supporting permit records
Fees, inspections, and companion permits
These describe the public permit record, not total design, construction, utility, or professional costs.
Department timing
Average first-review response
Calendar days from application to each department’s first dated response.
Active permits
Why permits are waiting now
A snapshot of the latest public review state, not proof that anyone forgot.
Issued permits
How long issuance took
Distribution from application date to issued date for completed permits in this selection.
Data quality
How much of the live sample is enriched
Coverage is published with each snapshot so missing optional data is not mistaken for zero activity.
Read this before comparing
Useful benchmarks, not promises.
The analysis starts with Bellevue BS “New House or Large Addition” permits published by MyBuildingPermit, then uses the public project description to retain 503 new-home permits and exclude identifiable large additions. This is a new-home cohort, not a count of every Bellevue building permit. Averages exclude records without the dates needed for that metric.
The dataset checks for newly filed projects daily, refreshes existing project details on a rolling monthly schedule, and rebuilds this analysis every Sunday. Inspection and status detail may therefore lag the public record by up to about a month.
Projects are classified from the public description and grouped by parcel, project name, and application year so multi-building developments can be identified. Custom and spec builder comparisons include only builders with a reviewed label and recalculate with each weekly snapshot. Builder names may be missing or incomplete, and small samples should not be treated as a quality ranking.
Bellevue does not publish the exact date a permit becomes Ready to Issue. “Final approval to issue” is therefore a proxy: issued date minus the latest final department approval date.
Construction measures use substantive dated inspections after issuance and exclude canceled, scheduled, preconstruction, job-conference, and job-start rows. Issuance-to-final timing includes only permits already finaled. Other parcel permit records can include unrelated historical work and are not treated as confirmed companion permits.
Build Eastside provides this benchmark analysis for free under its Terms of Use.