BEBuild Eastside

Bellevue permit data

What 499 new-home permits reveal.

See how long recent Bellevue permits took, which city teams responded first, how often plans needed changes, and where active permits are waiting. Filter by builder for more context, but remember that every project is different.

499 qualifying new-home permitsApplications from Nov 2024 through Nov 2026Updated Nov 6, 2026
5.3 days

to the first dated response from any city department where activity data is available.

32.7 days

for every assigned department to finish the first review where the full round is public.

2.6 revision rounds

across permits with complete public review activity.

164 days

median application-to-issuance time among 303 permits with both dates.

New-home pipeline

New permit applications over time

Count new-home permit applications by application date. Switch between months and weeks to see whether the permitting pipeline is growing or shrinking.

15 more applications in the latest complete month. Oct 2026: 23, compared with 8 in Sep 2026. That is 188% higher.

Known spec buildersOther or unclassified builders

Nov 1, 2026 through Nov 6, 2026 (partial period). 4 total: 1 known spec, 3 other or unclassified applications.

Hover, focus or tap a bar to see its counts. Weeks run Monday through Sunday. The current period is partial through Nov 6, 2026 and is excluded from the comparison. The chart uses the full city sample, regardless of the builder filter below.

View counts and how to read them

Known spec builders have a reviewed spec-builder label. Other includes custom builders, unreviewed builders and records with no builder identified. Labels reflect the latest analysis and can change as builders are reviewed.

These are collected new-home applications, not a complete census of city permits. Counts include single-family homes, homes with an ADU, middle housing and multi-building developments. Each permit is counted once, regardless of status. One permit can cover multiple homes. Applications may be canceled or never become homes for sale.

Application counts are an early signal of possible future supply. They do not measure issued permits, finished homes or listings. A zero means no qualifying application was found in the collected records for that period.

Monthly new-home permit applications
PeriodKnown specOther or unclassifiedTotal
Nov 1, 2025 through Nov 30, 202551217
Dec 1, 2025 through Dec 31, 2025151328
Jan 1, 2026 through Jan 31, 2026161026
Feb 1, 2026 through Feb 28, 202614822
Mar 1, 2026 through Mar 31, 202611819
Apr 1, 2026 through Apr 30, 202671320
May 1, 2026 through May 31, 202671017
Jun 1, 2026 through Jun 30, 2026131023
Jul 1, 2026 through Jul 31, 2026101323
Aug 1, 2026 through Aug 31, 202661824
Sep 1, 2026 through Sep 30, 2026448
Oct 1, 2026 through Oct 31, 202622123
Nov 1, 2026 through Nov 6, 2026 (partial)134

Read and share the Bellevue and Kirkland monthly permit digest →

Showing the full 499-permit sample. 276 permits currently have a reviewed custom or spec builder label.

Permits analyzed499303 issued
Average time to issue182.2 daysIssued permits only
First city response5.3 daysEarliest department response
Complete first review32.7 daysAll assigned departments
Revision rounds2.6Observed public rounds
Final approval to issue26 daysEstimated proxy

Builder comparison

Timing across the full sample

Custom and spec groups use reviewed builder labels and recalculate with every weekly snapshot. Spec builders often repeat teams and processes, but the public data cannot isolate why one group was faster or slower.

Average time to issue
Selected
182.2 days
All builders
182.2 days
Complete first review
Selected
32.7 days
All builders
32.7 days
First city response
Selected
5.3 days
All builders
5.3 days
Revision rounds
Selected
2.6
All builders
2.6

Project mix

What is being built

Normalized from the public project description so unlike projects can be separated.

New single-family house355 permits
Duplex or middle housing73 permits
New house with ADU69 permits
Multi-building development2 permits

Construction

Issued permit to final approval

Based on 97 permits with both issued and finaled dates.

Median construction duration281 daysIssued through finaled
Average construction duration297.9 daysCalendar days

Location context

Where projects are concentrated

Neighborhood names come from the public parcel geocoder and are directional rather than formal boundaries.

Lake Hills7 permits
Bridle Trails3 permits
Northwest Bellevue3 permits
West Bellevue3 permits
Cougar Mountain-Lakemont1 permits
Newport1 permits
Northeast Bellevue1 permits
Somerset1 permits
West Lake Sammamish1 permits
Willburton1 permits

Supplemental parcel context

Most common assessor zoning labels

These labels support broad comparisons only and are not city zoning determinations. Confirm current zoning in Bellevue's official map.

SR-4288 permits
SR-279 permits
SR-354 permits
LL-130 permits
SR-127 permits
LL-221 permits

Supporting permit records

Fees, inspections, and companion permits

These describe the public permit record, not total design, construction, utility, or professional costs.

Average listed permit fees$21,090499 permits with fee data
Median inspections9499 permits checked
Average related permits8.6Other records found on the parcel

Department timing

Average first-review response

Calendar days from application to each department’s first dated response.

Building structural79.7 days
11 permits with dated activity
Land use23 days
472 permits with dated activity
Clearing & grading21.5 days
473 permits with dated activity
Building21.2 days
472 permits with dated activity
Utilities19.4 days
473 permits with dated activity
Right-of-way10.7 days
473 permits with dated activity
Fire8.4 days
473 permits with dated activity

Active permits

Why permits are waiting now

A snapshot of the latest public review state, not proof that anyone forgot.

Revisions waiting on architect110
City review in progress38
Owner issuance steps33
Reviews complete; awaiting city status7
One department still reviewing6

Issued permits

How long issuance took

Distribution from application date to issued date for completed permits in this selection.

90 days or less27 permits
91 to 120 days48 permits
121 to 180 days101 permits
181 to 240 days64 permits
More than 240 days63 permits

Data quality

How much of the live sample is enriched

Coverage is published with each snapshot so missing optional data is not mistaken for zero activity.

Permit detail100%
People and builders100%
Review activity100%
Fees100%
Inspections100%
Related permits100%
Optional parcel context100%

Same city. Same project category.

Are similar permits taking more or less time?

Compare application-to-issuance durations for permits issued in two consecutive periods. We use the latest six complete calendar months and the six months before them.

Earlier: Nov 1, 2025 through Apr 30, 2026.
Recent: May 1, 2026 through Oct 31, 2026.

Calendar days from application to issuance. Counts include only records with valid dates.
Project categoryEarlier periodRecent periodObserved change
New single-family house184 days median
95 permits
176.5 days median
56 permits
7.5 days shorter
New house with ADU164 days median
10 permits
132 days median
21 permits
32 days shorter
Duplex or middle housingMore data needed
1 permits
195.5 days median
16 permits
Not enough data to compare
How to interpret this comparison

Each median requires at least 10 permits. Categories are inferred from public descriptions. These are broad comparisons, not individually matched homes. Size, site conditions, review complexity and builder mix can still differ.

Only issued permits are included. Open permits and missing or invalid dates are excluded. A backlog clearing or changes in which records we collect can shift the median. These are collected records, not a complete census of city permits.

Durations include city review, design-team revisions and owner steps. A shorter duration does not prove the city became faster or predict your permit. The observed difference is descriptive, not a statistical significance test.

Overall activity

The latest 90 days compared with the prior 90

This overview mixes project categories. Use the comparable-project section for a category-specific comparison. Issuance timing is grouped by when a permit was issued. First-review timing is grouped by when that review finished.

Latest 90 days

Aug 10, 2026 through Nov 7, 2026

Applications
53
Issued
28
Median time to issue
218.5 days
Median first review
27.5 days

Previous 90 days

May 12, 2026 through Aug 9, 2026

Applications
60
Issued
63
Median time to issue
153 days
Median first review
26 days

Comparable projects

Permit timing by project type

Separating a single house from an ADU or multi-building project makes the benchmark more relevant. Small groups should be treated as directional.

Project typePermitsIssued sampleMedian to issueAverage first reviewAverage revision rounds
New single-family house355254165 days34.3 days2.9
Duplex or middle housing7317207 days30.7 days2.8
New house with ADU6932141.5 days26.3 days2.7
Multi-building development20Small sample25 daysNot enough data

Plan corrections

Timing by observed revision rounds

Median application-to-issuance time for completed permits. This shows an association and does not claim each revision caused all of the difference.

1 revision round125.5 days
52 permits in this comparison
2 revision rounds135 days
99 permits in this comparison
3+ revision rounds184.5 days
128 permits in this comparison

First-review bottleneck

Which department finished last

The department with the final dated response in a completed first review. A higher count does not mean that team performed poorly.

Land use152 permits
152 permits in this comparison
Clearing & grading97 permits
97 permits in this comparison
Building95 permits
95 permits in this comparison
Utilities85 permits
85 permits in this comparison
Right-of-way8 permits
8 permits in this comparison
Fire6 permits
6 permits in this comparison
Building structural3 permits
3 permits in this comparison

Who has the next action

City, design team, issuance, or unclear

Based on the latest public review state for active permits. Issuance requirements are kept separate from plan corrections, and incomplete activity records are labeled unclear rather than guessed.

Design team110 permits
City51 permits
Issuance requirements33 permits

Parcel permit history

Timing by other permit records on the parcel

Median time to issue grouped by how many other permit records MyBuildingPermit returned for the parcel. These can include unrelated historical work, so this is context rather than a true companion-permit count.

No other parcel records243 days
5 permits in this comparison
1 to 2 other parcel records173 days
11 permits in this comparison
3+ other parcel records164 days
287 permits in this comparison

Additional complexity signals

Timing by size, parcel, zone, and neighborhood

Project size and story count are extracted from public descriptions, while lot size, zone, and neighborhood come from matched parcel records. These are descriptive groupings, not proof that one characteristic caused a delay.

SignalGroupPermitsIssued sampleMedian to issueMedian revision rounds
Lot size7,000 to 9,999 sq ft234172156 days2
Lot size10,000 to 19,999 sq ft17889159 days2
Lot size20,000+ sq ft7334201.5 days3
Assessor zoning labelSR-4288189162 days2
Assessor zoning labelSR-27946178 days3
Assessor zoning labelSR-35429148 days3
Assessor zoning labelLL-13018Directional sample190 days3
Assessor zoning labelSR-12711Directional sample159 days2
Assessor zoning labelLL-22110Directional sample215 days3

Groups with fewer than ten issued records are withheld; groups with 10 to 19 are directional. Project-size and story comparisons appear only when the current parser can classify at least 60% of issued permits. Missing description or parcel fields are not inferred.

Repeat-builder experience

Timing by permit volume in this sample

Median time to issue based on how often the same normalized builder name appears. This measures observed volume, not whether the same staff or plans were used.

Builder appears once205.5 days
48 permits in this comparison
Builder appears on 2 to 4 permits174 days
68 permits in this comparison
Builder appears on 5+ permits151 days
163 permits in this comparison

Slower-permit patterns

Share that took longer than the upper quartile

Overlapping project characteristics among issued permits. These are descriptive flags, not a prediction that a future permit will be slow.

Custom home builder35.3%
17 permits in this comparison
Duplex or middle housing29.4%
17 permits in this comparison
2+ revision rounds27.5%
251 permits in this comparison
New single-family house25.2%
254 permits in this comparison
3+ other parcel records23.7%
287 permits in this comparison
Spec home builder20.1%
174 permits in this comparison
New house with ADU18.8%
32 permits in this comparison

After issuance

Construction and inspection benchmarks

These measures describe the public inspection record after issuance. They do not include unrecorded jobsite work, contractor scheduling, or private quality-control checks.

Issue to first substantive inspection36 days265 permits with both dates
Typical inspection cadence7.7 daysMedian average gap between distinct inspection dates
Repeated correction checkpoint61.5%Same public checkpoint recorded with 2+ correction outcomes
Issue to final281 days97 finaled permits

Field-inspection timing excludes canceled, scheduled, preconstruction, job-conference, and job-start rows. A correction includes public outcomes containing “correction,” “failed,” or “denied”; “Not Ready for Inspection” is not counted as a city correction. A repeat requires two correction outcomes at the same normalized public checkpoint. The cadence metric calculates each project's average gap between distinct inspection dates, then reports the median project. Metrics with fewer than ten permits are withheld. These projects come from the same 24-month application cohort as the rest of this page.

Listed permit fees

Use the range, not just the average

Publicly listed permit fees only. These figures do not include architecture, engineering, construction, utility, or other project costs.

Lower quarter$12,67625th percentile
Median$23,379Middle of 499 permits
Upper quarter$26,29375th percentile
Average$21,090More sensitive to unusually large fees

Read this before comparing

Useful benchmarks, not promises.

The analysis starts with Bellevue BS “New House or Large Addition” permits published by MyBuildingPermit, then uses the public project description to retain 499 new-home permits and exclude identifiable large additions. This is a new-home cohort, not a count of every Bellevue building permit. Averages exclude records without the dates needed for that metric.

The dataset checks for newly filed projects daily and refreshes existing project details on a rolling monthly schedule. Successful discovery, detail and status-refresh batches recalculate this analysis automatically. Sunday recalculation remains a safety net. A recent analysis date does not mean every underlying record was fetched that day.

Projects are classified from the public description and grouped by parcel, project name, and application year so multi-building developments can be identified. Custom and spec builder comparisons include only builders with a reviewed label and recalculate with each successful analysis. Builder names may be missing or incomplete, and small samples should not be treated as a quality ranking.

Bellevue does not publish the exact date a permit becomes Ready to Issue. “Final approval to issue” is therefore a proxy: issued date minus the latest final department approval date.

Construction measures use substantive dated inspections after issuance and exclude canceled, scheduled, preconstruction, job-conference, and job-start rows. Issuance-to-final timing includes only permits already finaled. Other parcel permit records can include unrelated historical work and are not treated as confirmed companion permits.

Build Eastside provides this benchmark analysis for free under its Terms of Use.

Practical worksheet

Put this guide to work

Worksheet updated . This is a planning example. Regulatory sources and data have their own dates.

Use the numbers without turning them into a promise

A completed-permit median of five months does not mean a currently reviewed permit has five months remaining. It describes the midpoint of a particular completed group. A first-review target measures a different interval and may exclude correction time.

Comparable scope
Choose the same city and permit family. Check new house versus addition, review complexity, sample size and the observation period.
Matching milestones
Identify the start and end dates, business or calendar days, excluded periods and whether the data includes applicant response time.
Current next step
Estimate remaining work from the latest meaningful event and open reviews. Keep consultant response commitments separate from city targets.
Uncertainty
Use a range and note missing information. Active permits are unfinished observations, not failed or completed cases, and small samples can be unstable.

Treat a comparison as a planning aid and a reason to ask better questions. Do not rank a city, architect or builder by elapsed time alone without accounting for project scope, corrections, owner decisions and incomplete records.