Bellevue permit data

What 504 new-home permits reveal.

See how long recent Bellevue permits took, which city teams responded first, how often plans needed changes, and where active permits are waiting. Filter by builder for more context, but remember that every project is different.

504 qualifying new-home permitsApplications from Sep 2024 through Sep 2026Updated Sep 15, 2026
5.1 days

to the first dated response from any city department where activity data is available.

34.1 days

for every assigned department to finish the first review where the full round is public.

2.5 revision rounds

across permits with complete public review activity.

159 days

median application-to-issuance time among 325 permits with both dates.

Showing the full 504-permit sample. 292 permits currently have a reviewed custom or spec builder label.

Permits analyzed504325 issued
Average time to issue182.3 daysIssued permits only
First city response5.1 daysEarliest department response
Complete first review34.1 daysAll assigned departments
Revision rounds2.5Observed public rounds
Final approval to issue26.3 daysEstimated proxy

Builder comparison

Timing across the full sample

Custom and spec groups use reviewed builder labels and recalculate with every weekly snapshot. Spec builders often repeat teams and processes, but the public data cannot isolate why one group was faster or slower.

Average time to issue
Selected
182.3 days
All builders
182.3 days
Complete first review
Selected
34.1 days
All builders
34.1 days
First city response
Selected
5.1 days
All builders
5.1 days
Revision rounds
Selected
2.5
All builders
2.5

Project mix

What is being built

Normalized from the public project description so unlike projects can be separated.

New single-family house374 permits
Duplex or middle housing67 permits
New house with ADU61 permits
Multi-building development2 permits

Construction

Issued permit to final approval

Based on 111 permits with both issued and finaled dates.

Median construction duration295 daysIssued through finaled
Average construction duration312.3 daysCalendar days

Location context

Where projects are concentrated

Neighborhood names come from the public parcel geocoder and are directional rather than formal boundaries.

Northwest Bellevue6 permits
West Bellevue6 permits
Lake Hills5 permits
Newport5 permits
Bridle Trails3 permits
Northeast Bellevue1 permits
Somerset1 permits
West Lake Sammamish1 permits
Willburton1 permits

Supplemental parcel context

Most common assessor zoning labels

These labels support broad comparisons only and are not city zoning determinations. Confirm current zoning in Bellevue's official map.

SR-4294 permits
SR-277 permits
SR-355 permits
LL-128 permits
SR-125 permits
LL-221 permits
LDR-23 permits

Supporting permit records

Fees, inspections, and companion permits

These describe the public permit record, not total design, construction, utility, or professional costs.

Average listed permit fees$21,467504 permits with fee data
Median inspections5504 permits checked
Average related permits8.6Other records found on the parcel

Department timing

Average first-review response

Calendar days from application to each department’s first dated response.

Building structural84 days
11 permits with dated activity
Clearing & grading22.6 days
472 permits with dated activity
Land use22.5 days
465 permits with dated activity
Building21.6 days
474 permits with dated activity
Utilities19.5 days
465 permits with dated activity
Right-of-way10.2 days
476 permits with dated activity
Fire8.3 days
481 permits with dated activity

Active permits

Why permits are waiting now

A snapshot of the latest public review state, not proof that anyone forgot.

Revisions waiting on architect107
City review in progress39
Owner issuance steps32
One department still reviewing1

Issued permits

How long issuance took

Distribution from application date to issued date for completed permits in this selection.

90 days or less28 permits
91 to 120 days54 permits
121 to 180 days112 permits
181 to 240 days66 permits
More than 240 days65 permits

Data quality

How much of the live sample is enriched

Coverage is published with each snapshot so missing optional data is not mistaken for zero activity.

Permit detail100%
People and builders100%
Review activity100%
Fees100%
Inspections100%
Related permits100%
Optional parcel context99.8%

Same city. Same project category.

Are similar permits taking more or less time?

Compare application-to-issuance durations for permits issued in two consecutive periods. We use the latest six complete calendar months and the six months before them.

Earlier: Sep 1, 2025 through Feb 28, 2026.
Recent: Mar 1, 2026 through Aug 31, 2026.

Calendar days from application to issuance. Counts include only records with valid dates.
Project categoryEarlier periodRecent periodObserved change
New single-family house184 days median
109 permits
179 days median
71 permits
5 days shorter
New house with ADUMore data needed
6 permits
139 days median
22 permits
Not enough data to compare
Duplex or middle housingMore data needed
1 permits
More data needed
9 permits
Not enough data to compare
How to interpret this comparison

Each median requires at least 10 permits. Categories are inferred from public descriptions. These are broad comparisons, not individually matched homes. Size, site conditions, review complexity and builder mix can still differ.

Only issued permits are included. Open permits and missing or invalid dates are excluded. A backlog clearing or changes in which records we collect can shift the median. These are collected records, not a complete census of city permits.

Durations include city review, design-team revisions and owner steps. A shorter duration does not prove the city became faster or predict your permit. The observed difference is descriptive, not a statistical significance test.

Overall activity

The latest 90 days compared with the prior 90

This overview mixes project categories. Use the comparable-project section for a category-specific comparison. Issuance timing is grouped by when a permit was issued. First-review timing is grouped by when that review finished.

Latest 90 days

Jun 18, 2026 through Sep 15, 2026

Applications
55
Issued
56
Median time to issue
173.5 days
Median first review
25 days

Previous 90 days

Mar 20, 2026 through Jun 17, 2026

Applications
65
Issued
43
Median time to issue
157 days
Median first review
28 days

Comparable projects

Permit timing by project type

Separating a single house from an ADU or multi-building project makes the benchmark more relevant. Small groups should be treated as directional.

Project typePermitsIssued sampleMedian to issueAverage first reviewAverage revision rounds
New single-family house374284164 days35.9 days3
Duplex or middle housing6712180 days30.2 days2.3
New house with ADU6129137 days25.4 days2.6
Multi-building development20Small sample25 daysNot enough data

Plan corrections

Timing by observed revision rounds

Median application-to-issuance time for completed permits. This shows an association and does not claim each revision caused all of the difference.

1 revision round123 days
53 permits in this comparison
2 revision rounds133 days
101 permits in this comparison
3+ revision rounds182 days
139 permits in this comparison

First-review bottleneck

Which department finished last

The department with the final dated response in a completed first review. A higher count does not mean that team performed poorly.

Land use137 permits
137 permits in this comparison
Clearing & grading110 permits
110 permits in this comparison
Building91 permits
91 permits in this comparison
Utilities80 permits
80 permits in this comparison
Fire6 permits
6 permits in this comparison
Right-of-way6 permits
6 permits in this comparison
Building structural4 permits
4 permits in this comparison

Who has the next action

City, design team, issuance, or unclear

Based on the latest public review state for active permits. Issuance requirements are kept separate from plan corrections, and incomplete activity records are labeled unclear rather than guessed.

Design team107 permits
City40 permits
Issuance requirements32 permits

Parcel permit history

Timing by other permit records on the parcel

Median time to issue grouped by how many other permit records MyBuildingPermit returned for the parcel. These can include unrelated historical work, so this is context rather than a true companion-permit count.

No other parcel records282 days
6 permits in this comparison
1 to 2 other parcel records172 days
16 permits in this comparison
3+ other parcel records158 days
303 permits in this comparison

Additional complexity signals

Timing by size, parcel, zone, and neighborhood

Project size and story count are extracted from public descriptions, while lot size, zone, and neighborhood come from matched parcel records. These are descriptive groupings, not proof that one characteristic caused a delay.

SignalGroupPermitsIssued sampleMedian to issueMedian revision rounds
Lot size7,000 to 9,999 sq ft246180156 days2
Lot size10,000 to 19,999 sq ft170101157 days2
Lot size20,000+ sq ft7335203 days3
Assessor zoning labelSR-4294201155 days2
Assessor zoning labelSR-27749177 days3
Assessor zoning labelSR-35530145 days3
Assessor zoning labelLL-12819Directional sample185 days3
Assessor zoning labelSR-12511Directional sample159 days3
Assessor zoning labelLL-22111Directional sample208 days4

Groups with fewer than ten issued records are withheld; groups with 10 to 19 are directional. Project-size and story comparisons appear only when the current parser can classify at least 60% of issued permits. Missing description or parcel fields are not inferred.

Repeat-builder experience

Timing by permit volume in this sample

Median time to issue based on how often the same normalized builder name appears. This measures observed volume, not whether the same staff or plans were used.

Builder appears once206.5 days
46 permits in this comparison
Builder appears on 2 to 4 permits153 days
61 permits in this comparison
Builder appears on 5+ permits151 days
179 permits in this comparison

Slower-permit patterns

Share that took longer than the upper quartile

Overlapping project characteristics among issued permits. These are descriptive flags, not a prediction that a future permit will be slow.

Duplex or middle housing41.7%
12 permits in this comparison
Custom home builder33.3%
21 permits in this comparison
2+ revision rounds28%
271 permits in this comparison
New single-family house25.4%
284 permits in this comparison
3+ other parcel records23.8%
303 permits in this comparison
Spec home builder20.1%
189 permits in this comparison
New house with ADU13.8%
29 permits in this comparison

After issuance

Construction and inspection benchmarks

These measures describe the public inspection record after issuance. They do not include unrecorded jobsite work, contractor scheduling, or private quality-control checks.

Issue to first substantive inspection36 days260 permits with both dates
Typical inspection cadence7.8 daysMedian average gap between distinct inspection dates
Repeated correction checkpoint67.3%Same public checkpoint recorded with 2+ correction outcomes
Issue to final295 days111 finaled permits

Field-inspection timing excludes canceled, scheduled, preconstruction, job-conference, and job-start rows. A correction includes public outcomes containing “correction,” “failed,” or “denied”; “Not Ready for Inspection” is not counted as a city correction. A repeat requires two correction outcomes at the same normalized public checkpoint. The cadence metric calculates each project's average gap between distinct inspection dates, then reports the median project. Metrics with fewer than ten permits are withheld. These projects come from the same 24-month application cohort as the rest of this page.

Listed permit fees

Use the range, not just the average

Publicly listed permit fees only. These figures do not include architecture, engineering, construction, utility, or other project costs.

Lower quarter$13,00825th percentile
Median$23,291Middle of 504 permits
Upper quarter$25,91975th percentile
Average$21,467More sensitive to unusually large fees

Read this before comparing

Useful benchmarks, not promises.

The analysis starts with Bellevue BS “New House or Large Addition” permits published by MyBuildingPermit, then uses the public project description to retain 504 new-home permits and exclude identifiable large additions. This is a new-home cohort, not a count of every Bellevue building permit. Averages exclude records without the dates needed for that metric.

The dataset checks for newly filed projects daily and refreshes existing project details on a rolling monthly schedule. Successful discovery, detail and status-refresh batches recalculate this analysis automatically. Sunday recalculation remains a safety net. A recent analysis date does not mean every underlying record was fetched that day.

Projects are classified from the public description and grouped by parcel, project name, and application year so multi-building developments can be identified. Custom and spec builder comparisons include only builders with a reviewed label and recalculate with each successful analysis. Builder names may be missing or incomplete, and small samples should not be treated as a quality ranking.

Bellevue does not publish the exact date a permit becomes Ready to Issue. “Final approval to issue” is therefore a proxy: issued date minus the latest final department approval date.

Construction measures use substantive dated inspections after issuance and exclude canceled, scheduled, preconstruction, job-conference, and job-start rows. Issuance-to-final timing includes only permits already finaled. Other parcel permit records can include unrelated historical work and are not treated as confirmed companion permits.

Build Eastside provides this benchmark analysis for free under its Terms of Use.

Practical worksheet

Put this guide to work

Worksheet updated . This is a planning example. Regulatory sources and data have their own dates.

Use the numbers without turning them into a promise

A completed-permit median of five months does not mean a currently reviewed permit has five months remaining. It describes the midpoint of a particular completed group. A first-review target measures a different interval and may exclude correction time.

Comparable scope
Choose the same city and permit family. Check new house versus addition, review complexity, sample size and the observation period.
Matching milestones
Identify the start and end dates, business or calendar days, excluded periods and whether the data includes applicant response time.
Current next step
Estimate remaining work from the latest meaningful event and open reviews. Keep consultant response commitments separate from city targets.
Uncertainty
Use a range and note missing information. Active permits are unfinished observations, not failed or completed cases, and small samples can be unstable.

Treat a comparison as a planning aid and a reason to ask better questions. Do not rank a city, architect or builder by elapsed time alone without accounting for project scope, corrections, owner decisions and incomplete records.