BEBuild Eastside

Bellevue permit data

What 300 building permits reveal.

Explore how long Bellevue permits take, which departments respond first, how many revision rounds are typical, and where active permits are waiting. Filter the results by builder to compare experience across the same public process.

300 recent permitsApplications from Jun 2025 through Jul 2026Updated Aug 7, 2026
About 5.7 days

to the first dated response from any city department.

About 31 days

for every assigned department to finish the first review.

2 revision rounds

on average across the full 300-permit sample.

163 days

from application to issuance among permits issued in the sample.

Showing the full 300-permit sample.

Permits analyzed300126 issued
Average time to issue163.5 daysIssued permits only
First city response5.7 daysEarliest department response
Complete first review30.6 daysAll assigned departments
Revision rounds2Observed public rounds
Final approval to issue15.4 daysEstimated proxy

Builder comparison

Timing across the full sample

Average time to issue
Selected
163.5 days
All builders
163.5 days
Complete first review
Selected
30.6 days
All builders
30.6 days
First city response
Selected
5.7 days
All builders
5.7 days
Revision rounds
Selected
2
All builders
2

Department timing

Average first-review response

Calendar days from application to each department’s first dated response.

Building Structural43.3 days
7 permits with dated activity
Land Use22.9 days
291 permits with dated activity
Building22.5 days
293 permits with dated activity
Clearing & Grading19.9 days
293 permits with dated activity
Utilities18.3 days
287 permits with dated activity
Right Of Way11.8 days
296 permits with dated activity
Fire8.3 days
300 permits with dated activity

Active permits

Why permits are waiting now

A snapshot of the latest public review state, not proof that anyone forgot.

Revisions waiting on architect95
City review in progress33
Owner issuance steps19
Reviews complete; awaiting city status15
One department still reviewing4

Issued permits

How long issuance took

Distribution from application date to issued date for completed permits in this selection.

90 days or less10 permits
91–120 days25 permits
121–180 days51 permits
181–240 days22 permits
More than 240 days18 permits

Read this before comparing

Useful benchmarks, not promises.

The analysis uses 300 recent Bellevue building permits and review activity published by MyBuildingPermit. Averages exclude records without the dates needed for that metric.

Builder names come from the supplied permit list and may be missing or incomplete. Small builder samples can swing dramatically, so they should not be treated as a quality ranking.

Bellevue does not publish the exact date a permit becomes Ready to Issue. “Final approval to issue” is therefore a proxy: issued date minus the latest final department approval date.