How long permits take in Redmond

Redmond publishes dependable timing for selected paths, but not one current comprehensive table for every permit type.

Reviewed against official Redmond sources, August 2026

Official timing source: Redmond Development Services. Review goals and workload can change, so recheck the source before fixing a schedule.

Published timing by permit type

Use the published figures only for the named process. Building timing depends on completeness, project coordinator routing, corrections, and the number of reviewing departments.

Permit or reviewRough timeWhat the number meansOfficial source
Simple same-day permitSame day when eligibleCity describes simple permit pathRedmond Development Services
Coordinated civil review28 days per review cycle; roughly 4 months for a clean, responsive projectCity FAQ estimateRedmond permit FAQ
Right-of-way use30–60 days after complete submittalCity FAQ estimateRedmond right-of-way permit FAQ
Building, trade, fire, tree, and land-use permitsNo comprehensive current public table foundConfirm with the assigned coordinatorRedmond Development Services

Build a realistic total schedule

  • Start the city clock only when the official source says it starts: completeness, fee payment, routing, or first review.
  • Add time for intake, public notice, related permits, consultant review, and issuance if those steps are outside the published figure.
  • Keep applicant correction time separate from city review time.
  • Use a range rather than one promised date, and refresh the estimate after every correction round.
  • Where the city publishes no target, ask for current workload after the application is accepted.