Before you submit in Medina
How to schedule a Medina predevelopment meeting before you apply
Medina has the most structured early-meeting process of these four cities. It encourages owners planning new houses, additions, and remodels to use an online predevelopment meeting, and offers a separate development information meeting for non-owners researching a parcel.
Contact details and official sources checked August 2026The short answer
Choose the correct Wednesday meeting, upload the request form through Medina's permit portal by noon the prior Thursday, and include preliminary plans when applying for a predevelopment meeting. The city currently requires a $2,000 advance deposit for either meeting; unused funds are refunded after consultant costs are reconciled.
Official starting point: Medina Start Here. Verify hours, fees, availability, staff, and forms before acting because city services can change.
Choose the correct Medina meeting
- Predevelopment meeting: for owners and applicants preparing a building permit such as a new house, addition, or remodel. Include preliminary site or building plans.
- Development information meeting: for a party other than the owner who is studying zoning and development limitations on a parcel, such as a prospective buyer.
- Both are early guidance, not a completeness determination, code approval, vested application, or guarantee of a permit outcome.
Schedule through the permit portal
Medina holds the meetings online on Wednesday mornings, subject to availability. Download the correct fillable form, choose a preferred Wednesday time, and upload the form to the city's SmartGov permitting portal. Predevelopment requests must include preliminary plans or other project documents. The published cutoff is noon on the Thursday before the requested Wednesday.
- The current predevelopment form lists 8:30, 9:30, and 10:30 a.m. preferences.
- Create or use a SmartGov account before the cutoff so portal access does not become the scheduling problem.
- Confirm availability and current charges with Development Services before relying on a date.
Understand the $2,000 deposit
Medina states that a $2,000 advance deposit is collected for either meeting. The deposit reimburses the city for consultant time as costs are incurred. The city says a remaining balance is refunded approximately three months after the meeting. Treat $2,000 as a deposit, not necessarily the final cost, and ask how billing and refunds will be documented.
Prepare for a multi-discipline discussion
Depending on the project, Medina may make its Planner, Development Services Coordinator, Building Official, Tree Code Consultant, Grading and Drainage Consultant, and Development Services Director available. Staff may email checklists after the meeting.
- Start with Medina Title 16 zoning and a parcel-specific concept.
- Bring a survey or site plan, preliminary floor plans and elevations, trees, grading and drainage concept, access, utilities, and known easements.
- Separate questions by zoning, building, trees, grading/drainage, and application documents.
- Record every caveat and follow-up; discussions are nonbinding.
Direct contacts and City Hall
- Steven Wilcox, Development Services Director: 425-233-6409, swilcox@medina-wa.gov.
- Rebecca Bennett, Development Services Coordinator: 425-233-6414, rbennett@medina-wa.gov.
- City Hall: 501 Evergreen Point Road, Medina, WA 98039; main phone 425-233-6400.
- Published City Hall business hours: Monday through Friday, 8 a.m. to 4 p.m. Schedule the formal online meeting through the portal rather than assuming a walk-in review is available.
Action plan
How to get a useful answer
- 1
Decide whether you need the owner/applicant predevelopment meeting or the non-owner feasibility meeting.
- 2
Download the current request form and review Medina Title 16 before fixing the concept.
- 3
Prepare the preliminary plans and a numbered list of high-value questions.
- 4
Upload the form and documents through SmartGov by noon Thursday before the requested Wednesday.
- 5
After the meeting, combine staff checklists and notes into the future permit-submittal matrix.