After permit issuance
Bellevue building inspections: a homeowner closeout checklist
An issued permit is permission to build, not proof the project is finished. The permit closes only after the required work is inspected and the final approvals are recorded.
Reviewed against official sources · August 2026Create the inspection sequence before work starts
Have the contractor turn the approved plans and permit conditions into an inspection schedule. Identify work that cannot be covered before inspection, special inspections, utility or right-of-way signoffs, and any required preconstruction meeting.
Be ready before calling
- Approved plans and permit documents are available at the site.
- The inspector has safe access and on-site parking.
- The work is complete for the requested inspection and has not been covered.
- Corrections from earlier inspections have been resolved.
- The responsible contractor or knowledgeable representative can answer questions.
Track corrections like permit revisions
Record the correction, owner, due date, required document, and reinspection date. If field conditions require a design change, ask whether revised plans must be approved before the inspector can sign off.
Close every related permit
Do not stop after the building final. Confirm electrical, mechanical, plumbing, fire, utilities, clearing-and-grading, and right-of-way permits are final where applicable. Bellevue says final building signoff authorizes occupancy for a typical house unless a certificate of occupancy is specifically required.
Protect the permit timeline
Bellevue instructs permit holders to begin work within one year of issuance and complete it within three years. Keep inspection records and raise schedule risks early rather than assuming an open permit can sit indefinitely.
Action plan
Close the permit without last-minute surprises
- 1
Download the issued plans, permit conditions, and inspection list.
- 2
Ask the contractor for an inspection sequence tied to the construction schedule.
- 3
Do not cover work until the required inspection is approved.
- 4
Log every correction, owner, due date, and reinspection result.
- 5
Confirm final approval for every related permit before final payment and occupancy.
Official resources