Before paying for plans
Get a free first-pass feasibility study for your own address. See what may fit and what to confirm next.
Check my propertyIllustrative scenario · Kirkland
Follow a hypothetical Kirkland RS 8.5 rebuild through FAR, setbacks, lot coverage, and the conditions behind garage allowances.
This first pass assumes no special allowance. It has not screened the lot for trees, easements, critical areas, shoreline rules, or private restrictions.
| Check | Calculation | What it tells you |
|---|---|---|
| Base FAR ceiling | 8,500 × 0.50 = 4,250 sq ft | A ceiling on counted floor area. The garage is counted in this screen. |
| Desired counted floor area | 4,000 + 500 = 4,500 sq ft | 250 sq ft above the base FAR ceiling. Other counted areas may affect the final result. |
| Lot coverage ceiling | 4,250 sq ft | Includes structures and defined hardscape. It is not a building-footprint-only limit. |
| Rectangle after base setbacks | (85 − 15) × (100 − 20 − 10) = 4,900 sq ft | A geometric screen. This area does not override FAR, coverage, or site constraints. |
A 4,000 sq ft home plus a 500 sq ft garage totals 4,500 sq ft. The base RS 8.5 FAR ceiling for this assumed lot is 4,250 sq ft. A qualifying detached garage behind the main structure can have an exclusion, and a conditional design bonus may apply. Neither is assumed here. A designer must establish the conditions before using either allowance.
Example published . Confirm the current code and any project-specific conditions with the City.
RS 8.5 base FAR, lot coverage, height, and yards, with table footnotes.
Counted floor area, conditional garage exclusions, and the design-based FAR bonus.
What counts toward Kirkland lot coverage.
Get a free first-pass feasibility study for your own address. See what may fit and what to confirm next.
Check my propertyCheck your permit’s status. Create a free account to get alerts when it changes.
Check and monitor my permit