Bellevue ADU and detached ADU rules
Can I build an ADU or DADU in Bellevue?
Many qualifying Bellevue properties can support one or two ADUs, either inside or attached to the main home or in a separate detached building. The practical question is which option fits your lot and your plans. The answer depends on setbacks, FAR, lot coverage, trees, critical areas, utilities, and Bellevue's August 2026 ordinance package, which is newer than the online codification.
Quick definitions. An accessory dwelling unit (ADU) is a complete additional home on the same property. A detached ADU (DADU) is in its own building. FAR or GFA limits how much enclosed floor area the property may contain.
Bottom line
What the current rules mean
Bellevue allows up to two ADUs on a qualifying residential lot. Most may contain up to 1,200 square feet, with up to 300 square feet of parking or unheated storage excluded from that size limit. An attached ADU can be an addition or part of the existing house; a DADU is a separate building. That choice matters because attached ADU floor area is exempt from FAR and does not increase the FAR dwelling count, while a detached ADU counts toward both the lot's dwelling count and its FAR calculation.
On this page8 sections
Common homeowner questions
Answers to common Bellevue ADU questions
Can I add an ADU to my Bellevue home?
Often, yes. Bellevue allows attached and internal ADUs on qualifying residential lots. The unit can be created within the existing house or as an addition, but it must be a complete legal dwelling and meet building, utility, access, and permit requirements. Attached ADU floor area is exempt from FAR and does not increase the FAR dwelling count, which can make an addition worth comparing with a detached unit when the main house is already close to the lot's floor-area limit.
Can I build a detached ADU (DADU) in Bellevue?
Bellevue permits detached ADUs citywide on qualifying residential sites, and a lot may support up to two ADUs when all dwelling-count and site rules are met. Most DADUs are limited to 1,200 square feet and 24 feet high, or 28 feet when an ADU is added above an existing accessory structure. A DADU counts toward the lot's dwelling count and FAR, and a new ADU is not allowed on a unit lot created or developed through a unit-lot approval.
What setbacks apply to a Bellevue DADU?
The side setback is generally five feet, while front and rear setbacks depend on the zoning district. Current front setbacks range from 10 to 25 feet and rear setbacks from 10 to 15 feet. An alley can allow a zero setback, but easements, building separation, fire access, critical-area buffers, and tree-protection areas may require more room than the zoning setback alone.
How do FAR and lot coverage affect an ADU addition or DADU?
They are separate fit tests. An attached ADU's floor area is exempt from FAR and does not raise the FAR dwelling count. A DADU counts toward FAR but also moves the property into the applicable multi-dwelling FAR tier. The entire project must still meet structure coverage plus the district's hard-surface and impervious-area limits, so additional FAR does not guarantee that a detached footprint will fit.
Can trees or critical areas prevent a Bellevue DADU?
Yes. Significant or landmark trees, including protection areas for trees near a property line, can occupy the apparent backyard building area. Wetlands, streams, flood areas, habitat, steep slopes, and geologic hazards can add buffers, studies, mitigation, or a Critical Areas Land Use Permit. Check these constraints together with setbacks rather than treating the open lawn as the buildable area.
How can I tell whether an ADU will fit on my Bellevue lot?
Compare more than the ADU size limit. A useful first screen needs the parcel's zoning, lot geometry, existing house and garage, legal units, remaining FAR and coverage, setbacks, trees, critical areas, easements, access, and utility routes. Build Eastside's free feasibility study starts with the address and the home you hope to create, then identifies which attached, conversion, or detached options deserve more design work.
Official sources: Bellevue LUC 20.20.120: accessory dwelling units · Bellevue Ordinance 6931 enactment · Bellevue LUC 20.20.390: floor area ratio · Bellevue LUC 20.20.538: middle-housing dimensions · Bellevue LUC Part 20.25H: critical areas · Bellevue LUC 20.20.900: tree retention · Bellevue LUC 20.50.020: FAR definitions · Bellevue 2026 tree-code update
What is allowed on one lot
LUC 20.20.120, as amended by Ordinance 6931, allows up to two ADUs on a lot in a district that permits a single-family dwelling or middle housing. They may be attached or detached. A detached ADU counts toward the maximum dwellings on the lot; an attached ADU does not. A new ADU is prohibited on a unit lot created or developed under a unit-lot approval, so parent-lot and unit-lot status must be checked first.
- Two attached or internal ADUs.
- One attached and one detached ADU.
- Two detached ADUs where dwelling count, FAR, coverage, trees, access, and building separation allow them.
- Conversion of a legal existing structure despite qualifying setback or coverage nonconformity; expansions need separate review.
Official sources: Bellevue LUC 20.20.120: accessory dwelling units · Bellevue Ordinance 6931 enactment · RCW 36.70A.681: limits on local ADU regulation
How much room the property may have for an ADU
- Maximum size
- The typical maximum is 1,200 square feet. The Director may allow more where an attached ADU occupies an entire floor of the principal dwelling or where an addition or conversion to an existing detached accessory structure meets the codified exception. A guest-cottage conversion without expansion is exempt. Up to 300 square feet per ADU of parking or unheated storage is excluded from the ADU size limit.
- Height
- A DADU is limited to 24 feet, or 28 feet when added above an existing accessory structure. An attached ADU uses the principal building's height standards.
- Setbacks
- A DADU follows the current middle-housing dimensions: front yards are 25 feet in LL-1, 20 feet in LL-2, and 10 feet from SR-1 through MDR-2; rear yards are 15 feet in LL-1, LL-2, SR-1 and SR-2, and 10 feet from SR-3 through MDR-2; side yards are five feet. A zero setback is allowed along an alley. Other zero common-side conditions are narrow and should not be assumed for an ordinary DADU.
- FAR, lot coverage, or impervious area
- Structure coverage is generally 40 percent in LL-1 through SR-3 and 45 percent in SR-4 through MDR. Hard-surface and impervious limits vary by district and must both be checked. Bellevue's FAR table depends on total dwelling count. An attached ADU's floor area is exempt and it does not increase the FAR unit count; a detached ADU counts. The limited FAR exemption for up to 300 square feet of parking or unheated storage per dwelling applies to qualifying middle housing, not automatically to an ordinary single-house garage. Current maximum FAR ranges from 0.5 for one dwelling on a lot of 10,000 square feet or less through 1.5 for six dwellings, with separate large-lot formulas.
Official sources: Bellevue LUC 20.20.120: accessory dwelling units · Bellevue LUC 20.20.010: base residential dimensions · Bellevue LUC 20.20.538: middle-housing dimensions · Bellevue LUC 20.20.390: floor area ratio
Parking, occupancy, renting, and separate sale
- Parking
- No ADU parking is required when the unit is below 1,000 square feet excluding garage area, or when it is within a half-mile walking distance of a qualifying major transit stop. Otherwise Bellevue requires one space per ADU.
- Owner occupancy
- Bellevue has no owner-occupancy requirement.
- Short-term rental
- Bellevue limits ADUs to stays of at least 30 days and prohibits using them for transient lodging under 30 days.
- Separate sale
- Separate condominium conveyance may be available, but there is no automatic fee-simple or unit-lot split. Parent-lot, unit-lot, title, lender, and condominium requirements need separate review.
Official sources: Bellevue LUC 20.20.120: accessory dwelling units · Bellevue rental-use requirements
Utilities, fire access, and the permit path
Applications use MyBuildingPermit. One or two dwellings in a structure generally use a residential BS permit, while three to six use the middle-housing path; multiple buildings may also need a separate clearing-and-grading/site permit. Sewer, storm, water, fire, septic/well, trade, critical-area, tree, and right-of-way approvals depend on the property and configuration.
- Confirm the current district, overlays, parent-lot or unit-lot status, legal existing units and structures, transit eligibility, and whether an earlier application is vested.
- Choose attached versus detached before calculating dwelling count, FAR, coverage, height, yards, parking, and tree credits; Bellevue treats the forms differently.
- Prepare a survey-based plan showing current grade, easements, utilities, trees and protection areas, critical areas and buffers, access, drainage, hard surface, and impervious area.
- Use the current BS or middle-housing building path and identify any separate site, clearing/grading, critical-area, tree, fire, utility, right-of-way, shoreline, or health approvals.
- Confirm current fees and utility connection or capacity costs rather than assuming an ADU-wide exemption.
Official sources: Bellevue new-house and large-addition permits · Bellevue middle-housing building permits · Bellevue permit fees and estimator
Rules that can change the answer for one property
A citywide ADU allowance does not prove that a detached unit fits on a particular lot. Resolve these items before buying plans or fixing the DADU location.
- Ordinances 6931–6933 took effect in early August 2026 and are newer than the currently codified online text; use the enactments and confirm vesting.
- A detached ADU changes the FAR dwelling count and tree-credit rate; an attached ADU does not.
- A new ADU is not permitted on a unit lot created or developed through a unit-lot approval, even though an ADU may be possible on the parent lot.
- Significant and landmark trees, including off-site or property-line protection areas, can eliminate the apparent DADU footprint.
- Wetlands, streams, flood areas, habitat, steep slopes and geologic hazards can require a Critical Areas Land Use Permit, reduced density, large buffers, or professional reports.
Official sources: Bellevue LUC 20.20.900: tree retention · Bellevue 2026 tree-code update · Bellevue LUC Part 20.25H: critical areas
Address-level ADU feasibility
What to check before assuming a detached ADU will fit
Start with the outcome you want: an ADU addition, a conversion inside the home, a converted garage, or a new backyard DADU. Bellevue treats those options differently. An address-level screen can compare them against the lot's remaining FAR and coverage, actual yards, tree-protection areas, mapped constraints, access, and utilities before you pay to adapt a plan.
Confirm the address is actually governed by Bellevue and select the correct base-zone standards.
Count the principal dwelling, existing legal ADUs, middle-housing units, and the proposed attached or detached configuration.
Use legal lot lines, front/rear designation, alleys, access easements, and existing structures rather than a tax-map rectangle.
Test the ADU against the rules that apply locally: FAR or GFA, building or lot coverage, impervious or hard surface, and landscaping.
Screen critical areas and buffers, shorelines, slopes, flood hazards, significant trees, drainage, and recorded easements.
Verify water, sewer or septic, fire flow, hydrant and apparatus access, power, meters, and trench routes.
The engine must not use the online codification alone until Ordinances 6931–6933 are incorporated. It should route unit-lot sites, critical areas, significant or landmark tree impacts, legal nonconforming conversions, and vesting to manual review.
Do not rely on the older rule
Two different kinds of old information are risky here: pre-June 2025 material that says detached ADUs are not allowed, and the codified website that has not yet incorporated Ordinances 6931–6933 effective in August 2026. The current guide overlays the adopted enactments on the code.
Primary sources
Official Bellevue and Washington references
These are the sources used for this guide. Check them again before filing because ordinances, fee schedules, and permit forms can change.
What to check first
- 1
Confirm the parcel is inside Bellevue city limits and identify its current zone.
- 2
Map the principal home, lot lines, easements, trees, utilities, driveway, critical areas, and buffers on one current survey.
- 3
Test the ADU footprint against setbacks, height, floor-area or coverage limits, hardscape, parking, and construction access.
- 4
Ask the utility providers to confirm water, sewer, power, meter, side-sewer, and capacity requirements before fixing the design.
- 5
Have the city confirm the complete land-use, building, fire, right-of-way, tree, and utility permit list in writing.
Practical worksheet
Put this guide to work
Worksheet updated . This is a planning example. Regulatory sources and data have their own dates.
Compare the configurations before picking a floor plan
A basement conversion, an attached addition and a detached backyard unit can have the same target living area but very different constraints. A conversion depends on the existing structure and usable headroom. A detached unit may create more utility trenching, access and tree conflicts. A pre-approved plan still needs a site-specific fit check.
- Option A: use existing space
- Ask the designer to evaluate structure, moisture, light, exits, fire separation and system capacity. Verify that the existing work is lawful rather than relying on a listing description.
- Option B: attach new space
- Check how the new area is counted with the primary home, how the roof and structure connect and whether occupied construction is practical.
- Option C: detach
- Test the permitted location, building separation, access, utilities, drainage and construction route. Include the whole property in coverage and tree calculations.
- Use and ownership
- Confirm the proposed rental duration, occupancy, addressing, utility arrangement and any separate-sale path under the current local rules. An ADU permit is not a completed subdivision or condominium process.
Request comparable budgets with the same inclusions: design, studies, permits, site work, utility upgrades, building work, taxes and contingency. A price for the prefabricated unit or shell is not the complete installed project cost.