More homes on one lot
Bellevue ADU and middle-housing permits: choosing the right path
The permit type depends on units per building, total units on the property, and whether the project uses one or multiple structures. Start with that diagram before assuming an ADU or middle-housing project follows a normal remodel path.
Reviewed against official sources · August 2026Count units two ways
Count the dwelling units in each individual structure, then the total across the parcel. Bellevue treats permitted ADUs as dwelling units for choosing the construction-permit path.
Match the building to the permit
- One or two dwelling units in a structure generally use a BS permit.
- Three to six dwelling units in one structure use Bellevue’s MH permit.
- Projects beyond the stated middle-housing limits follow the commercial multifamily path.
- Each independent building needs its own building permit.
Expect a separate site permit for multiple buildings
Where multiple buildings contain dwelling units, Bellevue may require a GD clearing-and-grading permit so access, fire, transportation, utilities, drainage, trees, and site compliance are reviewed together. Keep every building and site set coordinated.
Check the site systems early
Test parking and access, fire approach, utility capacity and meters, stormwater, refuse, private open space, trees, easements, and construction staging before investing in unit layouts. The site often determines the viable unit count.
Ask Bellevue to confirm the path
Because middle-housing rules and permit processes are relatively new, bring a simple site/unit diagram to the Permit Center or predevelopment review and get the expected permit list in writing before producing a full set.
Action plan
Choose the permit path before designing units
- 1
Draw every structure and count units per building and across the parcel.
- 2
Ask Bellevue to confirm BS, MH, commercial multifamily, and separate GD site permits.
- 3
Test access, fire approach, parking, utilities, drainage, trees, refuse, and open space.
- 4
Keep every building set coordinated with the shared survey and site/civil permit.
- 5
Track the related permits as one project so one review does not become an unseen blocker.